(a) No permit shall be issued by any administrative officer for the construction of any building or improvement requiring a permit in any area covered by a site development plan, Engineering Plan, or Stormwater Pollution Prevention Plan except in conformity with the provisions of this chapter and duly approved plans. No construction or site improvements shall be initiated until the site plan, engineering plan, and/or Stormwater Pollution Prevention Plan has been approved.
(b) Any site development may be revised and such revisions shall be accomplished in the same manner as the original approval, provided, however, that minor technical changes which do not substantially alter the original site plan may be authorized by the Zoning Administrator.
(c) Upon satisfactory completion of the required improvements the Director of Engineering shall release any remaining bonds.
(Ord. 37-15. Passed 6-22-15.)