1137.03 MAJOR SITE PLANS APPROVAL PROCESS.
   (a)   Application and Submittal Requirements. An application for a Major Site Plan shall be filed on a form provided by the Village. The applicant shall pay a fee in accordance with the adopted fee schedule. Major Site Plans shall meet the submittal requirements kept on file at the Village. The Zoning Administrator may waive any items if not applicable to the project.
   (b)   Procedure. An application for a Major Site Plan shall be submitted to the Zoning Administrator who shall review it for completeness and compliance with the Codified Ordinances. Major Site Plans that do not comply with the Codified Ordinances shall not be placed on the Planning and Zoning Commission's agenda. Submittal shall be thirty (30) days prior to the meeting date at which the Major Site Plan will be reviewed by the Planning and Zoning Commission.
   (c)   Action and Effect. Upon approval of a Major Site Plan, the Zoning Administrator shall sign and return a copy of the approved Plan. The approval is valid for twelve months from the signature date unless a Building Permit has been obtained for construction. A single extension, not to exceed six (6) months, may be given by the Planning and Zoning Commission upon written request by the applicant. The Planning and Zoning Commission has the discretion to deny the extension.
   The Planning and Zoning Commission may attach conditions to the approval of the Major Site Plan in order to preserve the public health, safety and welfare of Obetz.
(Ord. 37-15. Passed 6-22-15.)