916.32 STORMWATER POLLUTION PREVENTION PLAN REVIEW.
   (a)   No earth-disturbing activities shall be permitted until an acceptable plan has been filed with and approved by the City Engineer. All Stormwater Pollution Prevention Plan Permit Applications shall be submitted to the City of Oberlin Public Works Department. The Office of the City Engineer shall review the Stormwater Pollution Prevention Plan within thirty days of receipt and indicate its approval or disapproval. Notice of disapproval shall include the plan deficiencies.
   (b)   When the Stormwater Management Plan Permit has been issued as provided for in Section 916.22 and all of the requirements of the OEPA Construction General Permit have been met by the Applicant's Stormwater Pollution Prevention Plan, the City Engineer shall issue the Stormwater Pollution Prevention Plan Permit.
(Ord. 19-62 AC CMS. Passed 11-18-19.)