1315.09 WATER SUPPLY.
   (a)   Water supply improvements shall be installed by the subdivider in conformance with the Public Works Standards.
 
   (b)   Water mains shall have a diameter of at least eight (8) inches.
   (c)   Service line connections shall be provided for each lot from the water line to the edge of the public right-of-way as approved by the Director.
   (d)   Hydrants shall be installed by the subdivider in conformance with the Public Works Standards and as approved by the Director of Public Works and the Fire Chief of the City of Oberlin.
   (e)   Water main extensions shall be installed by the subdivider to the farthest point of the last lot being served by such water main except that, when extending across a corner lot, the main shall be extended into or across the intersecting right-of-way or easement to a point determined by the Director.
   (f)   Water mains shall be installed in a manner that will permit supplying all points from two directions unless otherwise approved by the Director.
   (g)   Valves shall be installed at intervals not exceeding 1000 feet along water mains and at each leg of intersecting mains.
(Ord. 96-82 AC. Passed 9-16-96.)