1121.15 PRECONSTRUCTION MEETING.
   (a)    It will be the developer's responsibility to make arrangements for a preconstruction meeting. All interested parties should be invited to attend. These include:
      (1)    The Street Commissioner or his or her agent;
       (2)    The developer and the developer's engineer;
      (3)    The contractor and his or her project supervisor;
       (4)    Public utility companies involved; and
       (5)    A representative of the Planning Commission.
   (b)    The meeting should cover the following:
      (1)    A general plan review;
      (2)    A statement from the contractor outlining his or her construction schedule; and
      (3)    A statement by each utility involved.
         (Ord. 143.221. Passed 11-5-79.)