(A) The town will review each application for a site development permit to determine its conformance with the provisions of this regulation. Within 30 days after receiving an application, the town shall, in writing:
(1) Approve the permit application;
(2) Approve the permit application subject to such conditions as may be necessary to secure substantially the objectives of this regulation, and issue the permit subject to these conditions; and
(3) Disapprove the permit application, indicating the reason(s) and procedure for submitting a revised application and/or submission.
(B) Pending preparation and approval of a revised plan, development activities may be allowed to proceed if conditions established by the town are agreed upon.
(Ord. 2029, passed 4-18-2006)