(A) Description.
(1) Furnish and install all equipment for the lift station(s) including all structures, pumps, piping and controls as shown on the drawings and as described herein.
(2) The contractor shall be required to supply the pumps and control panel from a single manufacturer.
(B) Performance requirements.
(1) Lift station pumps shall be capable of passing a three-inch solid sphere.
(2) Pumps shall meet the design conditions and motor conditions specified on the plans.
(C) Submittals. The contractor shall be required to submit two copies each of the manufacturer’s operation and maintenance manuals and dimensional and technical shop drawing data to the town for all equipment supplied under this section.
(2004 Code, Art. II, § D, part 1)