§ 80.12 INSPECTIONS.
   (A)   (1)   All construction shall be subject to periodic inspections by the Building Commissioner irrespective of whether a building permit has been or is required to be obtained. The inspections are to be performed in a manner as being necessary to insure full compliance with the provisions of this chapter and the terms of any permit, if obtained. The Building Commissioner will make the following inspections for dwellings, businesses, educational buildings, institutional buildings, church buildings, and industrial, warehouse, and/or bulk storage buildings:
         (a)   Footing;
         (b)   Framing;
         (c)   Plumbing and heating;
         (d)   Electrical and heating; and
         (e)   Final.
      (2)   Reinspections of work found to be incomplete or not ready for inspection are subject to assessment of reinspection fees as prescribed in § 80.11(D). The Building Commissioner shall in all cases designate the stage of construction when each required inspection must be requested by the permit holder. The permit holder shall be responsible for notifying the Building Commissioner, orally or in writing, not less than 8 working hours, viz., the hours between 8:00 a.m. and 4:00 p.m., before covering or concealing work to be inspected. No concrete shall be placed for foundations, slabs, or floors without prior inspection. No electrical, mechanical, plumbing, thermal insulation, or structural framing shall be covered without prior inspection.
   (B)   A sticker or tag shall be attached to the building permit certifying each phase of construction or renovation. In cases where the work is not approved, the Building Commissioner shall cause a tag or sticker to be fastened to the building permit stating that the work is deemed in noncompliance. It shall be unlawful for any person to disturb or remove the tag until authorized to do so by the Building Commissioner. The permit holder shall repair or cause to be repaired defective work deemed in noncompliance to this code or documents listed in § 80.06 and shall notify the Building Commissioner after the work is completed so that reinspection can be made. No further work can progress until the previous phase of construction has been approved by the Building Commissioner.
(1989 Code, § 80.12) (Am. Ord. 020406, passed 2-4-2006)