1122.07 ACTION BY THE VILLAGE COUNCIL.
   (a)   Within forty-five (45) days after receiving the recommendation of the Planning and Zoning Commission, the Village Council shall meet to consider the proposed site plan and take one (1) of the following actions:
(1)   Approval of the site plan based upon a determination that the proposed plan will constitute a suitable development and is in compliance with the standards set forth in this Ordinance.
(2)   Disapproval of the site plan based upon a determination that the proposed project does not meet the standards for review set forth in this Ordinance.
(3)   Approval of the site plan subject to any conditions, modifications, and restrictions that will ensure that the project meets the standards for review.
   (b)   If the site plan is disapproved, the specific basis for such disapproval shall be provided along with clear description of how the site plan could be modified to be approved. Any re-submission of a site plan need only be submitted to the Village Council for review, after adjoining property owners previously notified have been provided a ten (10) day notice by first class mail of such a subsequent meeting.
(Ord. 2015-09. Passed 7-13-15.)