§ 52.04 PLAN SUBMITTAL REQUIREMENTS; PROCEDURES.
   The following procedures are to assist the applicant in permit application, plan submittal and permit issuance.
   (A)   Establishments required to install a grease interceptor shall submit the following to the utility office:
      (1)   A completed FOG discharge permit questionnaire;
      (2)   Detailed calculations by A & E firm, licensed engineer or competent design professional showing size of the grease interceptor. An example of grease interceptor sizing is contained in Appendix A, division (A);
      (3)   A complete list of all fixtures. For all sinks, list dimensions and drain sizes. For all dishwashers, list discharge flow rates as determined by the manufacturer’s specifications; and
      (4)   Plans showing:
         (a)   Location and size of all sanitary sewer lateral lines from the building to the lateral connection at the sanitary sewer main, location of grease interceptor, inverts and elevations of all pipes and structures and the location of all cleanouts;
         (b)   Fixture plumbing;
         (c)   Grease interceptor detail showing correct sizing information;
         (d)   FOG recycling barrel(s)/container(s) location(s); and
         (e)   Grease interceptor sizing calculation sheet.
   (B)   Two copies of required submittals shall be submitted to the Utility Office for approval. Utility approval must be obtained prior to the initiation of construction.
(Ord. 2012-20, passed 8-22-2012)