§ 155.039 LEVEL II STORMWATER MANAGEMENT AND SEDIMENT CONTROL PLAN REQUIREMENTS.
   The Level II Stormwater Management and Sediment Control Plan shall contain the following, as applicable:
   (A)   Completed application form and construction schedule with a certification by the person responsible for the land disturbance that the land disturbance will be accomplished pursuant to the plan and that Newberry County has the right to conduct on-site inspection.
   (B)   An anticipated starting and completion date of the various stages of land disturbance and the expected date the final stabilization will be completed.
   (C)   A description of the sediment control measures to be used during land disturbance. These activities are required to utilize best management practices to control erosion and sediment, and to utilize appropriate measures to control the quantity of stormwater runoff;
   (D)   A general description of topographic and soil condition of the tract;
   (E)   A general description of adjacent property and a description of existing structures, building and other fixed improvements located on surrounding properties, and;
   (F)   A sketched plan (engineer's, landscape architect's or surveyor's seal not required) to accompany the narrative shall contain:
      (1)   A site location drawing of the proposed project, indicating the location of the proposed project in relation to roadways, jurisdiction boundaries, streams, and rivers.
      (2)   The boundary lines of the site on which the work is to be performed;
      (3)   the location of temporary and permanent vegetation and structural erosion and sediment control measures.
(Am. Ord. 06-21-05, passed 6-15-2006)