The Level I Stormwater Management and Sediment Control Plan shall contain the following, as applicable:
(A) Complete application form and clearing schedule with a certification by the person responsible for the land disturbance that the land disturbance will be accomplished pursuant to the plan and that Newberry County has the right to conduct on-site inspections;
(B) An anticipated starting and completion date of the various stages of land disturbance activities and the expected date the final stabilization will be completed;
(C) A description of the sediment control measures to be used during land-disturbing activities. These activities are required to utilize appropriate measures to control the quantity of stormwater runoff.
(Am. Ord. 06-21-05, passed 6-15-2006)