A. Rough or Precise Grading Permit. The city engineer may issue a rough or precise grading permit for grading work upon completion of an application in accordance with Subarticle 3.1 of the Grading Manual. The issuance of building permits shall be determined as follows:
1. Building permits may be issued for a site graded under a precise grading permit upon completion and approval of the rough grade inspection as specified in Subarticle 7.6 of the Grading Manual.
2. Building permits shall not be issued for a site graded under a rough grading permit unless a precise grading permit has been issued.
B. Stockpile Permit. Upon approval by the city engineer, a stockpile permit may be issued for the stockpile of soil materials on a lot or parcel, provided that the soil materials shall be removed from the site or compacted and graded thereon under a subsequently issued rough or precise grading permit within six (6) months of issuance of a stockpile permit, unless modified by the city engineer, in accordance with Subarticle 4.3 of the Grading Manual.
(Ord. 349 § 4 (part), 2006: Ord. 346 § 4(part), 2006)