All street signs of standard design approved by the city shall be provided and installed by the subdivider. Street lighting as required shall be provided and installed by the subdivider.
(Ord. 274, passed 4-15-1997) Penalty, see § 153.999
A concrete curb and gutter of a design approved by the engineer shall be installed by the subdivider on each side of the streets indicated in the plat.
(Ord. 274, passed 4-15-1997) Penalty, see § 153.999
All required improvements shall be inspected by the engineer during construction at the expense of the subdivider.
(Ord. 274, passed 4-15-1997) Penalty, see § 153.999
FINANCIAL ARRANGEMENTS
Prior to the approval of a final plat by the governing body, the subdivider shall have agreed, in the manner set forth herein to install, in conformity with approved construction plans and in conformity with all applicable standards and ordinances, the following improvements on the site:
(A) Survey monuments;
(B) Grading;
(C) Pavements;
(D) Water mains;
(E) Public sanitary sewer;
(F) Drainage facilities; and
(G) Miscellaneous facilities and other improvements as required.
(Ord. 274, passed 4-15-1997)
The improvements as listed elsewhere are to be furnished and installed at the sole expense of the subdivider. However, if any improvement installed within the subdivision will be of substantial benefit to lands beyond the boundaries of the subdivision, provision may be made for causing a portion of the cost of the improvement, representing the benefit to such lands, to be assessed against the same. In such a situation, the subdivider will pay only for such portion of the whole cost of said improvements as will represent the benefit to the property within the subdivision.
(Ord. 274, passed 4-15-1997)
(A) Prior to the installation of any improvements and prior to approval of the plat, the subdivider shall enter into a contact in writing with the city requiring the subdivider to furnish and construct said improvement at his or her sole cost and in accordance with plans and specifications and usual contract conditions. This shall include provision for supervision of details of construction by the engineer, and shall grant to the engineer authority to correlate the work to be done under said contract by any subcontractor authorized to proceed thereunder and with any other work being done or contracted by the community in the vicinity. The agreement shall require the subdivider to make an escrow deposit or, in lieu thereof, to furnish a performance bond, the amount of the deposit or penal amount of the bond to be equal to one hundred twenty-five percent (125%) of the engineer’s estimate of the total cost of the improvements to be furnished under the contract, including the cost of inspection.
(B) No subdivider shall be permitted to start work on any other subdivision without special approval of the governing body if he or she has previously defaulted on work or commitments.