(A) The Planning Commission shall determine whether to approve or deny approval of a proposed interim management plan within 60 days of the city's acceptance of a proposed plan for filing, unless the operator consents to a longer period. The Planning Commission shall approve a proposed interim management plan if it finds, based on substantial evidence, that the interim management plan is consistent with the requirements of SMARA, the regulations promulgated thereunder, and this chapter.
(B) If the Planning Commission does not approve a proposed interim management plan, the city shall notify the operator in writing of any deficiencies in the plan. The operator shall have 30 days from such notice, or any longer period mutually agreed upon by the Planning Commission and the operator, to submit a revised plan.
(C) The Planning Commission shall approve or deny approval of a revised interim management plan within 60 days of receipt.
(`83 Code, § 15.30.590) (Ord. 97-03 § 1, 1997)