§ 15.28.120 INSPECTIONS.
   (A)   The Engineer shall, when requested, make the inspections required in this section, and shall either approve that portion of the work completed or shall notify the permittee wherein the work fails to comply with this chapter. Where it is found by inspection that the soil or other conditions are not as stated or shown in the application, the Engineer may immediately order all work to cease until approval is obtained for a revised grading plan conforming to the existing conditions.
   (B)   Plans for grading work, bearing the stamp of approval of the Engineer, shall be maintained at the site during the progress of the grading work and until the work has been approved. The permittee shall notify the Engineer in order to obtain inspections in accordance with the following schedule and at least 24 hours before said inspection is to be made:
      (1)   Initial inspection. When the permittee or his agent is ready to begin work on an excavation or fill;
      (2)   Rough grading. When all rough grading has been completed;
      (3)   Special structures. When excavations are complete for retaining and crib walls and when reinforcing steel is in place and before concrete is poured;
      (4)   Final inspection. When all work, including slope planting and installation of drainage and other structures has been completed.
   (C)   Compaction of fills which were approved by the engineer in accordance with § 15.28.180 shall be inspected by a registered soils engineer. A report prepared and signed by said soils engineer shall be submitted to the Engineer upon completion of the work and shall include the following:
      (1)   A contour map showing the original and finished surfaces of the areas filled, unless such map has previously been filed as part of the application for the grading permit;
      (2)   The foundation bearing values recommended for the compacted fill;
      (3)   A description of the materials used in the fill and the procedure of deposit and compaction, including the preparation of original ground surface before making the fill;
      (4)   A plan showing the location of tests made in the fill together with a tabulation of compaction test results;
      (5)   A statement that all work was done in conformance with the provisions of this chapter.
(`83 Code, § 15.28.120) (Ord. 85-11 § 1 (part), 1985)