(A) No permit to move any building upon the streets of the city shall be issued until all public utilities having wires or posts overhead, or above-ground structures along the proposed route have been notified and approval in writing of such approval is submitted to the Director of Community Development. The Director of Community Development, at his discretion, may refuse to issue a permit until a satisfactory solution to any problems has been provided.
(B) No permit to move a building upon or along the streets of the city shall be issued until the Police Department, the Fire Department, and the Public Works Department have been notified and have approved in writing, the proposed route along which said building is to be moved, and the proposed timetable for the moving of the structure upon or along city streets, including all periods of time during which the structure will be upon the city streets, whether in motion or stationary.
(`83 Code, § 15.24.090) (Ord. 88-08 § 1 (part), 1988)