§ 32.04  CLAIM COMPLETENESS REVIEW.
   (A)   Upon receipt of a claim, the city shall:
      (1)   Deny the claim if:
         (a)   It is not filed within five years from the date the land use regulation was enacted;
         (b)   An application for a comprehensive plan or zoning amendment is approved for the subject property; or
         (c)   Any submittal requirements are not met as set forth in § 32.02.
      (2)   Determine whether a claim is complete within 60 days after receiving the claim; and/or
      (3)   Notify the claimant of any missing information within 60 days after receiving the claim.
   (B)   After providing notice of missing information, the city shall:
      (1)   Deem the application complete if:
         (a)   The claimant provides the missing information and the required fee; or
         (b)    The claimant provides the required fee and a written statement that some or all of the missing information will not be provided.
      (2)   Deem the application complete if the city fails to notify the claimant of missing information within 60 days after receiving the claim; and/or
      (3)   Deem the application withdrawn if the claimant fails to provide the fee and the missing information, or a written statement that some or all of the information will not be provided within the time specified in the notice of missing information.
(Ord. 08-255, passed 3-4-2008)