§ 6-6.7 PRE-CONSTRUCTION CONFERENCE REQUIRED WHEN TOWN UTILITIES OVER- SIZED.
   (A)   The developer, design engineer, and contractor or a designated representative for each shall attend the pre-construction conference. If a representative for each of the parties is not in attendance, the pre-construction conference shall be rescheduled to a later date when each party can be represented.
   (B)   The developer, design engineer, and contractor or a designated representative for each, shall provide copies of all applicable federal, state, and local permits, easements, rights-of-way and encroachments and the appropriate engineering drawings to the Town Manager or designee for approval prior to the pre-construction conference.
(Adopted 7-10-2018)