2.03.010   Fees.
Each applicant for a PUD or an amendment to a PUD is required to reimburse the City for all of the City's costs for engineering, planning, and legal services relating to the consideration of the application and all City costs for notices. Following the pre-application conference, the City shall provide the applicant an estimated cost based on the nature of the application, which the applicant must pay at the time of application submittal.
If the City's actual costs exceed the estimate, the applicant will be required to pay the actual amount and if the actual costs are less than the estimate, the City will provide a partial refund to the applicant. No other fee is required for the processing and examination of the PUD application.
   (Ord. 711, passed 2-5-2019; Am. Ord. 716, passed 4-23-2019)