The following conditions shall apply to the compliance schedule required by § 54.101(B)(7):
(A) The schedule shall contain progress increments in the form of dates for the commencement and completion of major events leading to the construction and operation of additional pretreatment required for the IU to meet the applicable pretreatment standards. Such events include, but are not limited to, hiring an engineer, completing preliminary and final plans, executing contracts for major components and commencing and completing construction.
(B) No increment referred to in division (A) above shall exceed nine months.
(C) The IU shall submit a progress report to the director no later than 14 calendar days following each date in the schedule and the final date of compliance, including, at a minimum, whether or not the IU complied with the increment of progress to be met on that date, and, if not, the date it expects to comply, the reason for delay and the steps being taken by the IU to return to the established schedule.
(D) In no event shall more than nine months elapse between such progress reports to the director.
(Ord. 679, passed 9-26-2017)