909.58 ISSUANCE OF CONSTRUCTION PERMIT.
   Within forty-five days after submission of all plans and documents required of the applicant and payment of the permit fees required by this chapter, the Mayor, if satisfied that the applications, plans and documents comply with all requirements of this chapter, shall issue a permit authorizing the construction, reconstruction, installation, maintenance or repair of the facilities, or excavation in the public ways, subject to such further conditions, restrictions or regulations affecting the time, place and manner of performing the work as the Mayor may deem necessary or appropriate.
   Such forty-five day period shall begin only after all submissions are deemed by the Mayor to be in accordance with the requirements of this chapter, including information submitted in the form required by this chapter, and unconditional approval of construction drawings by the City Engineer.
(Ord. 1998-11. Passed 6-22-98.)