(A) Limitation on area. A right-of-way permit is valid only for the area of the right-of-way specified in the permit. No permittee may do any work outside the area specified in the permit, except as provided herein. Any permittee which determines that an area greater than that specified in the permit must be obstructed or excavated must before working in that greater area make application for a permit extension and pay any additional fees required thereby, and be granted a new permit or permit extension.
(B) Limitation on dates. A right-of-way permit is valid only for the dates specified in the permit. No permittee may begin its work before the permit start date or, except as provided herein, continue working after the end date. If a permittee does not finish the work by the permit end date, it must apply for a new permit for the additional time it needs, and receive the new permit or an extension of the old permit before working after the end date of the previous permit. This supplementary application must be submitted before the permit end date.
The excavation, backfilling, patching and restoration, and all other work performed in the right-of- way shall be done in conformance with Minn. Rules part 7819.1100, as it may be amended from time to time and other applicable local requirements, in so far as they are not inconsistent with M.S. §§ 237.162 and 237.163 as it may be amended from time to time.
(A) Notice of completion. When the work under any permit hereunder is completed, the permittee shall furnish a completion certificate in accordance Minn. Rule part 7819.1300, as it may be amended from time to time.
(B) Site inspection. The permittee shall make the work-site available to city personnel and to all others as authorized by law for inspection at all reasonable times during the execution of and upon completion of the work.
(C) Authority of Clerk.
(1) At the time of inspection, the Clerk may order the immediate cessation of any work which poses a serious threat to the life, health, safety or well-being of the public.
(2) The Clerk may issue an order to the permittee for any work which does not conform to the terms of the permit or other applicable standards, conditions, or codes. The order shall state that failure to correct the violation will be cause for revocation of the permit. Within ten days after issuance of the order, the permittee shall present proof to the Clerk that the violation has been corrected. If proof has not been presented within the required time, the Clerk may revoke the permit pursuant to § 94.40.
(A) Emergency situations.
(1) Each person with facilities in the right-of-way shall immediately notify the city of any event regarding its facilities which it considers to be an emergency. The owner of the facilities may proceed to take whatever actions are necessary to respond to the emergency. Within two business days after the occurrence of the emergency, the owner shall apply for the necessary permits, pay the fees associated therewith and fulfill the rest of the requirements necessary to bring itself into compliance with this chapter for the actions it took in response to the emergency.
(2) If the city becomes aware of an emergency regarding facilities, the city will attempt to contact the local representative of each facility owner affected, or potentially affected, by the emergency. In any event, the city may take whatever action it deems necessary to respond to the emergency, the cost of which shall be borne by the person whose facilities occasioned the emergency.
(B) Non-emergency situations. Except in an emergency, any person who, without first having obtained the necessary permit, obstructs or excavates a right-of-way must subsequently obtain a permit, and as a penalty pay double the normal fee for the permit, pay double all the other fees required by this code, deposit with the city the fees necessary to correct any damage to the right-of-way and comply with all of the requirements of this chapter.