(A) Sewer mains shall be inspected by closed-circuit television within two months of the end of the final guarantee period. Inspection shall be at the subdivider’s expense, with a detailed report in triplicate filed with the Superintendent of Public Works, prior to termination of the one-year guarantee.
(B) The applicant for the building sewer permit shall notify the Director of Community Development or his or her designee when the building sewer is ready for inspection and connection to the public sewer. The connection shall be made under the supervision of the Director of Community Development or his or her designee.
(Ord. 4107, passed 6-20-2011)