Sec. 82-115. Inspection required.
The city must be given notice when any new connection to the public sanitary sewer system is ready for inspection, and all work must be left uncovered and convenient for examination until inspected and approved. Such inspection shall be made within 24 hours after such notification. If the city inspector determines that any work constructed does not conform with this article, the sewer builder shall remove and replace any such rejected work and shall make all work meet the requirements of this article to the full satisfaction of the city inspector.
(Ord. No. 144, 5-16-2005)