§ 52.116 REQUIREMENTS FOR INSTALLATION; OTHER THAN VILLAGE.
   (A)   The village must approve all plans and specifications for any extensions.
   (B)   Before any extensions are installed, the plans and specifications must be reviewed and approved by the State Environmental Protection Agency.
   (C)   Ownership, rights-of-way and title must be conveyed to the village for all extensions installed by anyone other than the village. The village will maintain the mains thereafter.
   (D)   No extension will be permitted if, in the opinion of the Village Board, the system does not have necessary capacity to serve the proposed extension.
(`92 Code, § 38-5-57) (Ord. 77-10, passed 6-15-77; Am. Ord. 2024-03, passed 1-17-24) Penalty, see § 52.999