The Building and Zoning Administrator shall review all permit applications to determine whether proposed building sites will be reasonably safe from flooding. If a proposed building site is in a flood prone area, all new construction and substantial improvements (including the placement of prefabricated buildings and manufactured homes) shall:
(A) Be designed (or modified) and adequately anchored to prevent flotation, collapse, or lateral movement of the structure;
(B) Be constructed with materials resistant to flood damage;
(C) Be constructed by methods and practices that minimize flood damage;
(D) Be constructed with electrical, heating, ventilation, plumbing and air conditioning equipment and other service facilities that are designed and/or located so as to prevent water from entering or accumulating within the components during flooding.
(Ord. 2009-07, passed 4-1-09) Penalty, see § 157.99