§ 52.116 SEWER IMPROVEMENT AREA.
   (A)   (1)   Application for a building connection permit in the following locations, identified as sewer improvement areas, within which new construction is proposed, requires the following off-site sewer improvement cost recovery fee:
      (2)   No areas at this time.
   (B)   The foregoing off-site sewer improvement cost recovery fees are based on an equivalent dwelling unit basis where one dwelling unit is equal to a design average daily sanitary flow of 250 gallons per day, as determined by the Department. The off-site sewer improvement cost recovery fee will be paid to the Department at the time of or prior to the issuance of the building sewer permit.
   (C)   The Board of Mayor and Aldermen reserves the right to review the off-site sewer improvement cost recovery fee at least once a year and to adjust those fees as deemed necessary.
(Ord. passed 1-17-95; Am. Ord. passed 8-6-02; Am. Ord. passed 12-2-14)