§ 51.11 APPROVAL OF CONSTRUCTED FACILITIES.
   (A)   “as-built” drawings. 
      (1)   “As-built” drawings must be prepared and submitted by an Illinois professional engineer stating conformance with the design plans before final approval of the constructed improvements by the Administrator.
      (2)   Upon completion of construction of all stormwater detention facilities required and/or regulated by this chapter, all applicants shall deliver to the Administrator two complete sets of “as-built” plans, each sheet of which is clearly marked “as-built”. “As-built” plans shall depict the actual construction on the date of submittal of the plans. Said “as-built” plans shall also include a signed verification by the developer’s engineer that the stormwater detention and drainage facilities were constructed in accordance with the approved engineering plans and specifications and/or any modifications approved by the Administrator.
   (B)   (1)   Within 30 days after receipt of above said materials, the Administrator shall conduct a final inspection of the stormwater detention and drainage facilities required and/or regulated by this chapter. If the facilities are found to be satisfactory the Administrator shall approve in writing all constructed facilities which conform to the approved engineering plans and specifications, and shall give written notification of the approval to the applicant.
      (2)   The Administrator is authorized to reject any constructed facility which fails to conform to the approved plans and specifications. Upon such notification, the developer shall have 30 days in which to carry out any work required to bring the stormwater detention or drainage facility into compliance with the approved plans and/or specifications.
      (3)   Failure on the part of any applicant to so remedy any such non-compliance, may result in the village utilizing funds obtained from the performance guarantee to properly complete the improvements.
      (4)   Failure to properly complete the required stormwater detention and drainage facilities in a manner consistent with the approved engineering plans and specifications shall be considered a violation of this chapter.
(Ord. 15-12-02, passed 12-15-2015)