(A) Cost. Should the customer desire the service to be in a location other than stated, such extension if agreeable by MMED will be borne at the customer's expense. In any event, the cost for the extension shall be a minimum of ten dollars ($10.00) per running foot for three-phase and five dollars ($5.00) for singe-phase.
(B) New Residential Underground Services.
(1) MMED may install underground electric to any residential customer within any subdivision designated as an underground development.
(2) In addition to the customer-required facilities installation and contribution in aid of construction cost, a fee of two hundred dollars ($200.00) per lot per meter shall be paid prior to commencement of construction.
(C) New Commercial and Industrial Underground Service.
(1) MMED may install for any commercial or industrial customer an underground electric service upon request.
(2) In addition to the customer-required facilities installation and contribution in aid of construction cost, a fee of two hundred dollars ($200.00) per lot per meter shall be paid prior to commencement of construction.
(D) Underground Facilities to New Developments. In addition to the customer-required facilities installation and contribution in aid of construction cost, a fee of two hundred dollars ($200.00) per lot per meter shall be paid prior to commencement of construction.
(E) New Mobile Home Park Underground Service. In addition to the customer-required facilities installation and contribution in aid of construction cost, a fee of two hundred dollars ($200.00) per lot per meter shall be paid prior to commencement of construction.
(Ord. 2003-02, passed 1-21-03)