§ 155.47 PRE-CONSTRUCTION MEETING AND AUTHORIZATION.
   Prior to construction of the required improvements, the design engineer, contractors completing the improvements, and the developer shall meet with the City Engineer and the resident project representative. The developer shall submit to the City Engineer, during this meeting, a schedule of construction phases, shop drawings, installation of erosion control, and difficulties that may arise during construction. Shop drawings may be submitted ten work days prior to pre-construction meetings in order to have shop drawing approval by the meeting. Upon written consent of the City Engineer, the developer is authorized to proceed with construction.
(Ord. passed 5-22-03)