(A) Designation. Large Industrial High Consumption Rate Schedule (GS2GE).
(B) Availability. In any area served by the Madisonville Municipal Utilities (MMU) electric system in accordance with MMU’s terms and conditions for providing electric service.
(C) Application. To any large power customer for all electric power and energy requirements that do not fall below four thousand (4,000) kW average within a twelve (12) month period and a sixty percent (60%) load factor. In addition, the customer shall contract for year-round permanent service, and shall provide satisfactory guarantees or contribution to satisfy the expenditure necessary to provide the desired service. Each premises will be supplied only at one point of delivery and all electric service supplied will be measured through one meter. This schedule is not applicable for temporary, breakdown, standby, supplementary, resale or shared electric service.
(D) Type of service. Three phase, 60 hertz, with secondary voltages of 120/208, 120/240, 277/480, primary voltages of 7200/12470, or other voltages as might be mutually agreeable.
(E) Monthly rate.
(1) Customer charge: $2,587.50 per month.
(2) Demand charge: $16.909 per KW for each KW Billing Demand Energy.
(3) Charge: $0.055975 cents per KWH.
(F) Billing demand. Billing demand shall be greater of:
(1) The maximum fifteen (15) minute peak demand (kW) measured during the billing month;
(2) Sixty percent (60%) of the highest demand established in the preceding eleven (11) months; or
(3) Twenty percent (20%) of customer's Contract Demand (kW).
(G) Minimum bill. The minimum billing charge under the above rate shall be the established demand charge per the above criteria, energy, and customer charge or a customer charge plus a facilities investment charge of one dollar ($1.00) per kVA of installed transformer capacity as requested by the customer, whichever is greater.
(H) Power factor. This rate schedule is subject to a power factor charge as defined in the customer's energy services contract and/or this rate schedule.
(I) Fuel cost adjustment and power cost adjustment. The above rates are subject to a fuel adjustment cost (FAC) and/or a power cost adjustment (PCA) as specified in MMU's Rules and Regulations.
(J) Payment. Bills are due and payable when rendered and become delinquent on the fifteenth (15th) day after the date of issue. A penalty of ten (10%) percent may be added to all such bills.
(Ord. O-2022-11, passed 6-6-22)