§ 10-3.4.0105 REVIEW AND ACTION.
   (A)   Applications for site plan review which do not require action by the Planning Commission will be processed on a weekly basis. Complete applications received by 10:00 a.m. on Mondays will be processed and acted upon within eight working days. When the Monday is a holiday, submittals received by 10:00 a.m. on the preceding Friday will be processed in the stated time frame. The Community Development Director shall disperse plans to affected city departments and review agencies and coordinate the review process. On the eighth working day the Community Development Director shall notify the applicant in writing of approval, conditional approval, or disapproval of the application. The action of the Director shall be final unless appealed to the Planning Commission. The approved site plan, with any conditions shown thereon, or attached thereto, shall be dated and signed by the Director, with one copy mailed to the applicant and one copy filed with the Buildings Official.
   (B)   Applications for which Planning Commission approval is required or for which a negative declaration is mandatory, shall be submitted no later than 10:00 a.m. 29 calendar days prior to a regularly scheduled meeting. Applicants must be present at the Planning Commission meeting unless other arrangements are made. Written notification of the action of the Planning Commission will be mailed to the applicant within three working days following the meeting.
   (C)   Whenever required by the provisions of this chapter, or whenever deemed advisable by the Planning Commission or Community Development Director, a public hearing shall be held on an application. Public notice procedures shall be as follows:
      (1)   By one publication in a newspaper of general circulation in the city. Such notice shall state the name of the applicant, nature of the request, location of the property, the environmental determination, and the time and place of the action or hearing.
      (2)   Direct mailing to the owners and occupants of property located within 300 feet of the boundaries of the project site, as shown on the latest equalized assessment roll.
      (3)   In addition, notice shall also be given by first class mail to any person who has filed a written request with the Community Development Department. Such a request may be submitted at any time during, the calendar year and shall apply for the balance of such calendar year. The city may impose a reasonable fee on persons requesting such notice for the purpose of recovering the cost of such mailing.
      (4)   The public review period for the environmental determination (negative declaration) shall not be less than 21 calendar days (30 days if State Clearinghouse review is required).
      (5)   Substantial compliance with these provisions shall be sufficient and a technical failure to comply shall not affect the validity of any action taken pursuant to the procedures set forth in this chapter.
   (D)   While coordination of the review process is the responsibility of the Community Development Director, there may be circumstances, in the interest of expeditious review, where another department head may be requested to contact the project proponent regarding details of the site plan.
('61 Code, § 10-3.4.0105) (Ord. 507 C.S., passed 10-19-88; Am. Ord. 618 C.S., passed 3-16-94)