(A) The completion date may be extended by the City Council for subdivision of five or more parcels, and by the City Engineer for subdivision of four or less parcels, upon written request by the developer and the submittal of adequate evidence to justify the extension. The request shall be made not less than 30 days prior to expiration of the Subdivision Improvement Agreement.
(B) The subdivider shall enter into a Subdivision Improvement Agreement Extension with the city. For subdivisions of five or more parcels the agreement shall be prepared and signed by the City Engineer, approved as to form by the City Attorney, executed by the subdivider and transmitted to the City Council for their consideration. If approved by the City Council, the Mayor shall execute the agreement on behalf of the city.
(C) In consideration of a Subdivision improvement Extension Agreement, the following may be required:
(1) Revision of improvement plans to provide for current design and construction standards when required by the City Engineer;
(2) Revised improvement construction estimates to reflect current improvement costs as approved by the City Engineer;
(3) Increase of improvement securities in accordance with revised construction estimates;
(4) Inspection fees may be increased to reflect current construction costs but shall not be subject to any decrease or refund.
(D) The City Council may impose additional requirements as recommended by the City Engineer or as it may deem necessary as a condition to approving any time extension for the completion of improvements.
(E) The costs incurred by the city in processing the agreement shall be borne by the developer at actual cost.
('61 Code, § 10-2.711.3) (Ord. 252 C.S., passed 8-3-81)