§ 10-2.710.3 FINAL INSPECTION AND DEFICIENCY LIST.
   (A)   Upon completion of the subdivision improvements, the developer shall apply in writing to the City Engineer for a preliminary final inspection.
   (B)   A deficiency list shall be compiled during the inspection, noting all corrections or any additional work required. If the number of items are excessive or the subdivision appears incomplete, the preliminary final inspection may be halted and rescheduled on a date as determined by the City Engineer or authorized representative.
   (C)   When the preliminary final inspection has been completed, a copy of the deficiency list shall be transmitted to the developer for correction.
   (D)   Upon having completed all corrections or additional work as outlined by the deficiency list, the developer shall certify in writing that all corrections have been completed satisfactorily and request a final inspection. Forty-eight hours advance notice will be required for the City Engineer to schedule a final inspection.
   (E)   Upon finding that all items on the deficiency list have been corrected and as-built improvement plans have been received, the subdivision shall be placed on the Council Agenda for acceptance.
   (F)   The completion of corrections indicated by the deficiency list shall not relieve the developer from the responsibility of correcting any deficiency not shown on the list that may be subsequently discovered.
('61 Code, § 10-2.710.3) (Ord. 252 C.S., passed 8-3-81)