Permit # ____________________ Date: __________________
______ 1) No County Board action needed if:
a) Tower less than 200 feet (350 feet if over one and one-half mile from Decatur); and
b) Tower is at least the height of from nearest residence or, if over 99 feet tall, at least 100 feet or 80% of tower height, whichever is greater.
______ 2) Engineer’s written statement that antenna(s) complies with FCC regulations or radio frequency radiation (RFR). (§ 113.20(A))
______ 3) Engineer written statement that antenna(s) will not interfere with public safety telecommunications. (§ 113.20(B))
______ 4) Legal description of leased/dedicated land for tower. (§ 113.51(F))
______ 5) Certification by engineer as to structural integrity. (§ 113.51(D))
______ 6) Certification by engineer as to foundation plans. (§ 113.51(E))
______ 7) No part of “supporting structure or equipment housing” shall be less than 15 feet from front lot line of facility lot or ten feet from any other lot line. (§ 113.39(D))
______ 8) Site plan, to scale. (§ 113.51(C))
______ 9) Detailed description: tower height, facility height, number, and type of antennas that the proposed tower can accommodate. (§ 113.51(D))
(Res. G-1699-11-97, passed 11- -1997)