1324.08 MONITORING THE PERMIT FOR COMPLIANCE.
   (a)   Following the initial inspection of erosion and sediment control devices by the developer’s delegated representative, regular inspections (bi-monthly) will be performed by the City of Louisville for compliance with these Rules. If it appears that a violation of any of these Rules has occurred, the owner and developer will be notified of deficiencies or non- compliance in writing by certified mail, return receipt requested. If within 7 days after receipt of the letter, the owner or developer has not rectified the deficiency or received approval of plans for its correction, the deficiency or non-compliance may result in an injunction to cease work immediately until compliance with these rules.
   (b)   The City of Louisville may require revisions to the ESC plan as necessary to achieve compliance to these Rules.
   (c)   A final inspection will be made to determine if the criteria of these Rules have been satisfied.
(Ord. 12-27. Passed 5-7-12.)