913.036 SEWER CONNECTION INSPECTION.
   The applicant for the building sewer permit shall notify the Director of Utilities and the City Engineer or their representatives when the building sewer is ready for inspection and connection to the public sewer. All exterior foundations drains, roof downspouts, areaway drains, building drains, or building sewers shall be exposed and not backfilled so that all piping or connections can be inspected. Any person filling the trenches previous to inspection shall be required to re-excavate the trenches at his own expense before inspection, approval and connection to the public sewer can be made. The connection shall be made under the supervision of the Director of Utilities or the City Engineer or their representatives. One foot above the top of the pipe and the bedding around the pipe shall be granular material backfill or as directed by the City Engineer.
(Ord. 19-91. Passed 3-18-91.)