911.612 PROCEDURE FOR EXTENSION OF WATER MAINS WITHIN CITY.
   (a)   All new water MAIN extensions shall be initiated by Council and/or the Director of Public Service as herein mentioned in Section 911.610.
   (b)   All applications for new water MAIN extensions shall be submitted to the Director of Utilities and subject to approval by the Director of Public Service as mentioned in Section 911.610.
   (c)   All water MAIN extensions shall be engineered by the Engineering Division of the Division of Water of the City and/or Consulting Engineer authorized by Council and/or the Director of Public Service, subject to approval of the Director of Utilities and Director of Public Service. Exception will be that as is explained in Section 911.613.
   (d)   After all engineering plans have been completed and approved by the Director of Public Service, an ordinance will be submitted to Council by the Division of Water to authorize the installation of the water service MAIN and appropriate the monies required to pay the full cost of the water service MAIN. The full cost of the water service MAIN shall include all materials, including pipe, pipe fittings, valves, fire hydrants, etc., construction, engineering and inspection.
   (e)   The MAIN is then constructed by the contractor awarded the bid or by the construction forces of the Division of Water, as determined by the Director of Public Service and Director of Utilities.
   (f)   After sterilization and testing has been completed, applications for service will be accepted. (Ord. 167-96. Passed 9-16-96.)