§ 153.17 FINAL INSPECTION.
   (A)   A final inspection of all streets to be turned over to the city for maintenance must be inspected by the Director of Public Works or a designated inspector.
      (1)   The Director of Public Works should be contacted for scheduling of final inspections.
      (2)   When a phase/map of a subdivision reaches 80% occupancy, the phase/map will be considered eligible for acceptance by the city.
      (3)   The city may consider acceptance at an occupancy as low as 65%; however, in the case of early acceptance (<80%), the developer will be required to post, at minimum, a two-year maintenance bond.
   (B)   The procedures for requesting a final inspection are as follows:
      (1)   Submit a written request for final inspection.
      (2)   A representative from the city and/or designated inspector will proceed with the final inspection.
      (3)   Necessary repairs will be marked in the field, and indicated on a punch list, which shall be valid for a period of 30 days.
      (4)   When the necessary repairs have been completed, the city should be contacted to verify the repairs have been completed.
      (5)    When all conditions have been met, the developer may then proceed with requesting the city to accept the streets for maintenance.
(Ord. passed 8-8-2019)