§ 112.09 PERMITS, INSTALLATION, AND SERVICE.
   (A)   Within 30 days after the effective date of the franchise, the grantee shall proceed with due diligence to obtain all necessary permits and authorizations which are required in the conduct of its business including, but not limited to, any utility joint use attachment agreements.
   (B)   Within 90 days after obtaining all necessary permits, licenses, and authorizations, the grantee shall commence construction and installation of the CATV system.
   (C)   Within one year after obtaining all necessary permits and authorization, the grantee shall proceed to render to subscribers in at least 40% of the franchise area, and the completion of the system shall be pursued with reasonable diligence thereafter with extension of service to the remaining franchise area within the next succeeding year.
   (D)   Failure on the part of the grantee to commence and diligently pursue each of the foregoing requirements and to complete each of the matters set forth herein shall be grounds for termination of the franchise, under and pursuant to the terms of § 112.06; provided, however, the City Council may extend the time for the commencement and completion of construction and installation for additional periods in the event the grantee, acting in good faith, experiences delays by reason of circumstances beyond its control.
   (E)   The grantee shall, upon request, file a map with the city at the close of each franchise year, showing the areas and locations of the city being served by the CATV system and the location and identification of component parts of the system.
(Ord. 20, passed 8-5-1982)