(A) If the building official makes a finding based on substantial evidence that the electric vehicle charging station could have a specific adverse impact upon the public health or safety, as defined in this chapter, the city may require the applicant to apply for a use permit.
(B) In the technical review of an electric vehicle charging station, the building official shall not condition the approval for any electric vehicle charging station permit on the approval of such a system by an association, as that term is defined by Cal. Civil Code § 4080.
(Ord. 631, passed 9-19-2017)