After the installation of temporary block corner monuments and all underground facilities by the subdivider, and after the street grades have been established by the subdivider and submitted to the Board of Public Works for approval, streets shall be constructed by the subdivider in accordance with the following standards:
(A) Grading and graveling. The subdivider shall grade the full width of the right-of-way of all streets to be dedicated in accordance with plans and standard specifications approved by the Board of Public Works. The subdivider shall grade the pavement width to subgrade and surface with six inches of crushed stone plus six inches of gravel.
(B) Blacktopping. The year after the installation of the crushed stone and gravel in the roadway, the subdivider, at his or her expense, shall apply a standard 6-inch curb and 24-inch gutter and a full- width bituminous surface at a completed depth of at least 2½ inches, all in accordance with plans and specifications as approved by the Board of Public Works. In the event the pavement width of any street exceeds 40 feet, except for cul-de-sac turnarounds, the expense of installing the crushed rock, gravel, and blacktopping for the additional width shall be paid by the village.
(C) Curb and gutter. Prior to blacktopping, the subdivider shall install the standard 6-inch curb and 24-inch gutter in accordance with plans and specifications approved by the Board of Public Works. The subdivider shall pay 100% of the cost.
(`99 Code, § 8.09) Penalty, see § 153.999