§ 156.126 CERTIFICATE OF OCCUPANCY.
   (A)   No application for an improvement location permit under § 156.125 above may be considered unless the applicant has also applied for a certificate of occupancy.
   (B)   No land or structure with respect to which a permit has been issued under § 156.125 above may be used for the purpose contemplated by the permit unless the Administrator, after the change is completed, issues a certificate of occupancy stating that the change complies with this chapter and with the permit.
   (C)   Within ten days after the completion of the change authorized by the improvement location permit, the Administrator or his or her designee shall inspect the premises and, if the change conforms to this chapter and the improvement location permit, and a certificate of compliance, if required by § 156.129 below, has been obtained, he or she shall issue a certificate of occupancy.
(Ord. 614, passed 2-22-1999)