(a) At such time as the subdivider has completed the installation and construction of all public utilities and improvements required within the subdivision, they may seek acceptance for all such improvements by the City.
(b) The procedure for consideration of acceptance of public improvements shall be as follows:
(1) The individual or legal entity responsible for causing a public improvement to be constructed shall make a written request through the Department of Public Works that such public improvements be accepted by the City.
(2) One set of reproducible "as built" plans shall be submitted in conjunction with said written request.
(3) The Registered Professional Engineer of the project shall submit a written statement indicating that the off site improvements have been constructed in accordance with the approved plans, that the as built plans are a true and accurate representation of said off site improvements, and that the engineer is satisfied with off site improvements and the engineer recommends acceptance by the City.
(4) The Department of Public Works shall submit a written letter to the Mayor indicating the following:
A. That said improvements either have or have not been constructed in compliance with approved plans and specifications, and all requirements of the City of Lewisburg.
B. That the as built plans either provide or do not provide a true and accurate representation of the public improvements.
(5) Upon the Mayor's receipt of the Department of Public Works report, such report shall be submitted to the City Council for their acceptance of the improvements.
(6) If the City Council finds the public improvements and all associated requirements to be in compliance with these regulations, the improvements shall be accepted for maintenance.
(Passed 2-15-94.)