9-3-4: STORMWATER SYSTEM CONSTRUCTION:
   A.   Technical Requirements: Erosion and sediment control practices on construction sites shall meet the technical requirements as required in the stormwater construction permit.
   B.   Erosion And Sediment Control Practices: Erosion and sediment control practices shall be applied to all construction activities required by the stormwater construction permit including new development and redevelopment.
   C.   SWPPP Required: All construction activities listed under stormwater construction permit shall prepare a SWPPP in accordance with the permit. The SWPPP shall be submitted and reviewed by the City prior to application for the permit.
   D.   Erosion And Sediment BMPs: Erosion and sediment BMPs used for construction activities, listed on the SWPPP and sediment and erosion control plans shall protect water quality, reduce the discharge of pollutants, and control waste such as, but not limited to soils, sediment, oils, discarded building materials, concrete truck washout, chemicals, litter and sanitary waste that may cause adverse impact to water quality.
   E.   Meeting Requirements: Each application shall be accompanied by a SWPPP providing for erosion and sediment control and stormwater management during the land disturbing activity and after the activity has been completed meeting the requirements of stormwater general permit for construction activities permit.
   F.   Postconstruction Landscaping And Stabilization Requirements: Any area of land from which the natural vegetative cover has been either partially or wholly cleared by development activities shall be revegetated according to a schedule approved by the City Engineer. Stabilization must occur as required in the stormwater general permit for construction activities permit. (Ord. 99-2018, 11-13-2018)