8-1A-35: SITE PERMIT APPROVAL:
Upon approval of a site permit, a provider:
   A.   Shall complete the work approved within the permit and make the small wireless facility operational within two hundred seventy (270) days after the day on which the authority issues the permit, unless the lack of commercial power or communications facilities at the site delays completion;
   B.   Is authorized to operate and maintain any small wireless facility or utility pole covered by the permit for a period of ten (10) years from the date of approval; and
   C.   Is not authorized to install, place, or operate any other facility or structure in the right-of-way. (Ord. 77-2018, 8-28-2018)