8-1A-32: APPLICATION REVIEW PROCESS:
   A.   Review For Completeness: Upon receiving an application for the collocation of a small wireless facility or a new, modified, or replacement utility pole, the City shall determine within thirty (30) days if the application is complete. The City shall notify the applicant whether the application is complete.
   B.   Incomplete Application: If the City determines the application is incomplete:
      1.   The City shall identify the missing information in the written notification to the applicant; and
      2.   The review deadline in subsection A of this section shall be tolled from the day that the City sends the applicant written notice of the missing information or as the applicant and the City agree.
   C.   Shot Clocks: The City shall approve or deny a complete application within:
      1.   Thirty (30) days for the installation of an in-strand antenna;
      2.   Sixty (60) days for the collocation of a small wireless facility; or
      3.   One hundred five (105) days for a new, modified, or replacement utility pole.
   D.   Extension: The City may extend the shot clock deadline in this section for an additional ten (10) business days if the City notifies the applicant before the day in which the deadline expires.
   E.   Deemed Granted: If the City fails to approve or deny an application before its deadline, the application is deemed granted.
   F.   Denial: The City may deny an application that fails to meet the requirements of this chapter. If the City denies the application, the City shall notify the applicant of the denial and document the basis for the denial, including any specific laws on which the denial is based.
   G.   Cure: Within thirty (30) days of the City's denial, the applicant may cure any deficiency identified in the City's denial and resubmit its application without paying an additional application fee. The City shall approve or deny the resubmitted application within thirty (30) days of its receipt. The City may only review the portions of the application that were deficient or that have been changed. (Ord. 77-2018, 8-28-2018)