§ 5-2-5-11. OBSERVATION OF CONSTRUCTION OF SANITARY SEWERS.
   (A)   Execution of construction observation agreement. Prior to the commencement of construction, the applicant shall execute an agreement with the Board, which will provide that:
      (1)   The Board shall employ an observer of its choosing to observe the construction work to ensure that the construction meets the requirements of the approved construction plans;
      (2)   The observer will be responsible for submitting and certifying air pressure or infiltration test results for all pipe and deflection test results for all flexible pipe;
      (3)   The applicant will reimburse the City of Lawrence for the cost of the observation services which shall be determined at the time of execution of the agreement, with 50% of the estimated cost to be paid in advance on or before the date of approval of the permit, and the remaining balance to be paid when construction is completed;
      (4)   Upon completion of construction, the observer shall execute and file with the Board a certificate of completion and compliance certifying to the Board and the applicant as to the compliance of the construction with the requirements of the approved construction plans and/or approved change orders; and
      (5)   No action with regard to the acceptance of the construction and release of the improvement bond pursuant to this chapter shall be taken until the applicant has reimbursed the Board in full for the observation services.
   (B)   Observation of construction.
      (1)   All construction of sanitary sewers intended for dedication to the City shall be inspected and certified pursuant to the agreement executed under division (A) above.
      (2)   The applicant shall furnish the Board necessary copies of the approved construction plans.
      (3)   If construction has already commenced on the effective date of this chapter, the applicant must then furnish, along with a written request for acceptance, a certification by a professional engineer or land surveyor registered in the State of Indiana that the construction has met the requirements of the approved construction plans; further, the construction will be observed by the City Civil Engineer and all deficiencies shall be corrected prior to acceptance by the Board.