10.82.030   Multiple Permit Applications.
   A.   Concurrent Filing. An applicant for a development project that requires the filing of more than one application (e.g., Zoning Map Amendment and a Conditional Use Permit, etc.), shall file all related applications concurrently, together with all application fees required by Section 10.82.090 (Application Fees), below, unless the concurrent filing requirements are waived by the Director.
   B.   Concurrent Processing. Multiple applications for the same project shall be processed concurrently, and shall be reviewed, and approved or denied by the highest review authority designated by this Zoning Code for any of the applications (i.e., a project for which applications for Zoning Map Amendment and a Conditional Use Permit are filed shall have both applications decided by the Council, instead of the Commission acting upon the Conditional Use Permit as otherwise required by Table 6-1). In the example cited, the Commission would still hear each application (the Zoning Map Amendment and the Conditional Use Permit) and forward recommendations to the Council.
TABLE 6-1
REVIEW AUTHORITY
Applicable Code Chapter/Section
Role of Review Authority(1)
Type of Action
Director
Commission
Council
TABLE 6-1
REVIEW AUTHORITY
Applicable Code Chapter/Section
Role of Review Authority(1)
Type of Action
Director
Commission
Council
Administrative and Legal Actions
Development Agreements and Amendments
10.118
Recommend
Decision
General Plan Amendments
10.112
Recommend
Decision
Interpretations/Determinations
10.04
Decision(2)
Appeal
Appeal
Specific Plans and Amendments
10.120
Recommend
Decision
Zoning Code Amendments
10.112
Recommend
Decision
Zoning Map Amendments
10.112
Recommend
Decision
Planning Permits and Approvals
Conditional Use Permits
10.84
Decision
Appeal
Minor Use Permits
10.84
Decision(2)
Appeal
Appeal
Minor Variances
10.98
Decision(2)
Appeal
Appeal
Planned Development Permits
10.88
Decision
Appeal
Reasonable Accommodations
10.90
Decision(2)
Appeal
Appeal
Sign Permits
10.34
Decision(2)
Appeal
Appeal
Site Plan and Design Review
(See Table 6-2 for specified thresholds.)
10.94
Decision(2)
Decision/Appeal
Appeal
Temporary Use Permits
10.96
Decision(2)
(3)
Appeal
Variances
10.98
Decision
Appeal
Zoning Clearances
10.100
Decision
Appeal
Appeal
Notes:

(1)   “Recommend” means that the review authority makes a recommendation to a higher decision making body; “Decision” means that the review authority makes the final decision on the matter; “Appeal” means that the review authority may consider and decide upon appeals to the decision of an earlier decision making body, in compliance with Chapter 10.114 (Appeals).

(2)   The Director may choose to refer the application to the Commission for review and final decision, as authorized by this Zoning Code.

(3)   The City Manager shall serve as the first line of appeal for Temporary Use Permits in compliance with Subsection 10.96.080D. (City Manager to Act as Appeal Review Authority).
 
(Ord. 935 § 3 (part), 2015)